Saturday day shift 29 Nov:
Run 455 Trigger: hyp 9338 events
Stopped because of accellerator problems.
During day shift, Busso performed tests of the wiring of tofino,
and Paula has made the Bhabha trigger work again.
Run 4538 Cosmics - beam was on at low intensity during this test. LMD's
were turned off.
Run 4539 Cosmics: Same but LMD's on and tofino 9 and 12 switched off to
reduce the rate.